Overview

The Aurora Gold Mine is designed to produce 3.3 million ounces of gold, from the Open Pit mine and Underground Operations. SG Controls were engaged by Sedgman to provide E&I construction and commissioning services to the newly built Aurora Gold Project in Guyana, South America.

Profile

  • New Gold Mine and Process Plant
  • First major international project in Guyana
  • Average Annual Production (LOM) 220,000 oz Au

Capacity

  • Capacity of 6.4m Oz

Scope of Work

  • HV design review
  • Development of Switching Procedure
  • Power Station construction and installation
  • SAG Mill commissioning
  • Injection Testing
  • Management

Products Used

  • 240 watt Cummins Diesel Generators
  • Solomon Transformer Panels